高雄捷運工程介面整合與協調安裝之研究

Kaohsiung MRT project integration and coordination of the installation interface research

作者:邱勝麒
畢業學校:正修科技大學
出版單位:正修科技大學
核准日期:2010-02-09
類型:Electronic Thesis or Dissertation
權限:Copyright information available at source archive--CSU University....

中文摘要

高雄市大眾捷運系統以BOT模式特野褻※甽秧飪B公司承攬36年之興建、營運及轉移,工程興建期間拆分數個土建區段標及機電系統標,以統包模式交由各專業承攬廠商負責設計及建造,因所涉及各承攬商間之利益考量及設計施工方式皆不盡相同,且因工程進度急迫,工程及系統之設計、施工及系統安裝等以重疊方式進行,故各土建區段標間及與各系統標間之介面整合協調安裝作業之困難度程度極高且錯綜複雜。
本研究以高雄捷運土建標介面管理為例,蒐集相關文獻、期刊及論文資料,探討高雄捷運工程介面整體架構,以及土建標與系統標間設計及施工階段介面管理模式,將土建標實際面臨之介面整合管理方式及程序,歸納整理成下列研究項目:
一、土建標細設階段主導系統標介面整合及管理方式,運用項目辨識(IM)、時程登錄(IR)及資料交換(IDS)等作業流程研究。
二、土建標機電設備整合介面圖(CSD)及結構機電介面圖(SEM)介面彙整方式,介面需求資料交換及檢討流程研究。
三、土建標施工階段協調各系統標施作前置工作、設備進場及整合測試等介面協同作業之研究。

英文摘要

The Kaohsiung Mass Rapid Transit system authorized the folk Kaohsiung Rapid Transit Corp. to contract the constructing, transport business and shift by BOT for 36 years. The project constructing period to analyze several civil turnkey projects and the mechanical & electrical system projects by each special constructors to be responsible to design and construction. Because of involving contracts business respectively the benefit consideration and the design construction way all are different, and the project progress is so urgent. The civil work and the mechanical & electrical system all of design, construction and the equipment/system installment and so on are overlapping way to carry on, therefore it is very difficult and extremely complex for the interface conformity coordination.
This research in accordance with the civil interface management takes Kaohsiung Rapid Transit Corp.(KRTC) as an example. Collecting the related literature, the periodical magazines and thesis to research the interface overall construction management of KRTC s projects, additionally probe in the interface integration pattern of the civil project and the mechanical & electrical system one. The civil project should encounter the interface integration management and procedure, the generalization reorganizes the following research items:
First, research the design period, the civil project integrates the interface requirement of the mechanical & electrical system project by the procedure of Interface Matrix(IM)  Interface registration (IR)  Interface Data Sheet(IDS) completely.
Second, research the integrating pattern of the Combined Service Drawing (CSD) and the Structural, Electrical, Mechanical Drawing(SEM) according the civil engineering drawings, or the interface requirement and the procedure evolving.
Third, research the construction period, the civil constructor how to complete the interface coordination with the mechanical & electrical system ones as prepared work, equipment approach and conformity test etc..